Penthouse Development

Document Timeline

Penthouse Development

A Timeline - 2001 to 2025

It is important to remember that the lease to the roof spaces was sold to the Developer in 1997 and that our legal challenges to this sale ended in 2018. Although the Developer has the right to build on our roofs, we also have the right to protect the lives and property of Chiswick Village shareholders and leaseholders. It must also be remembered that when the penthouses are eventually sold, the owners of each penthouse will pay a Service Charge contribution, yet to be calculated by CVRL, and that CVRL will be responsible for the penthouses as part of the fabric of the whole of Chiswick Village.

The Developers frequently refer to blocks by number.

For clarity, the following is a simple guide translating relating block number to the flats they contain

Block 1 - Flats 1 to 16 Block 2 - Flats 17 to 36 Block 3 - Flats 37 to 56 Block 4 - Flats 57 - 76

Block 5 - Flats 77 to 100 Block 6 - Flats 101 to 118 Block 7 - Flats 119 to 142 Block 8 - Flats 143 - 160

Block 9 - Flats 161 to 184 Block 10 - Flats 185 to 204 Block 11 - Flats 205 to 220 Block 12 - Flats 221 - 236

Block 13 - Flats 237 to 252 Block 14 - Flats 253 to 268 Block 15 - Flats 269 to 280

September 2025 - Pi Consulting Report

Pi Consult, an engineering consultancy practice, was engaged by CVRL to review the documentation and drawings provided to CVRL to date, which have been completed by the various mechanical and electrical engineers employed by the developers.

Delivered in September 2025, a link to Pi Consult’s full report has been provided below. While we encourage all readers to read the entire report, some key statements stand out.

Roof Development Document Review Report – Page 3 - Summary and Findings

"Overall, the provided documentation is only completed up to concept stage with generic schematics and limited details that will not allow the successful installation of the MEP services and leaves so many gaps that Chiswick Village will not know what has been installed until the project is completed."

"Due to the lack of detailed design and the many associated gaps within the documentation which would prevent the current proposed scheme from achieving Building Regulations compliance, we have been unable to fully review the MEP documentation to a satisfactory level to allow us to advise our Chiswick Village client to proceed based on the current package."

"Currently this set of works together with the mechanical smoke ventilation systems are not included within the developer’s package. The costs of introducing these systems into the 15 blocks, together with backup Electrical supplies (typically being provided by generators) is cost prohibitive in our considered opinion to the Chiswick Village estate."

Pi Consult’s full report can be read here.

2025 - Continued

Sept 2025 - Penthouse Meeting - October 1st, 2025

Sept 2025 - London Penthouse Plans

Please note, the above link leads to a site owned and operated by the Developers, over which CVRL has no control

Sept 2025 - Developers Liability Insurance

Sept 2025 - Indicative Project Plan

Sept 2025 - Letter - Response to Developer Actions

Sept 2025 - Construction Management Plans

Sept 2025 - Lease - Roof Space Flats 1-16

Sept 2025 - Scaffold Plans - Blocks 4 to 6

Sept 2025 - Scaffold Plans - Block 7

Sept 2025 - Scaffold Plans - Blocks 8 to 11

2024

April 2024 - CVRL Newsletter 28

2022

October 17th, 2022Rooftop Development Project Report

This report was commissioned by CVRL from our then Mechanical and Engineering consultant, in response to draft plans from Airspace relating to the build of the Penthouses.  It focusses on all relevant heating, water and associated services where relevant. The report also contains a discussion about other services and features of the development, for example, insulation.

2019

October 2019 - CVRL Newsletter 23

2nd May 2019CVRL Letter to leaseholders re: upgrade to flat front doors

All further documents including leaseholder and resident consultation papers can be found here

1st March 2019CVRL Letter to leaseholders

2016

15th August 2016 - Annual General Meeting: Letter - 2016

Subsequent Annual Meetings are documented here

June 2016 - CVRL Newsletter 22

March 2016 - CVRL Newsletter 21

2013

10th October 2013 – CVRL – Letter of objection

7th October 2013 – CVRL – Notes of an open meeting held by CVRL

6th September 2013 – CVRL – Notice of Planning Application

25th July - 2013 - Matthew Consultants - Structural Report

Upchurch Associates, the architects engaged by the Developers at the time, invited Matthew Consultants to review their proposals for the extension of the buildings at Chiswick Village prior to formal submission to the local planning authority. This report provides initial structural proposals to support the development plans.

2011

9th August 2011 - CVRL AGM Review letter (see page 2)